Cox: New Allegany Still on Schedule

June 1st, 2017 by WCBC Radio

Although there have been some slight delays, overall construction on the new Allegany High School has been progressing smoothly. The project was held up last month after a critical brick delivery fell through- proving to be only a temporary delay.  The $51 million school on Haystack Mountain has three levels, currently all at various degrees of construction.  Maryland recently approved an additional $14 million toward the high school’s construction for fiscal 2018, leaving the balance for Allegany High School at $4 million. Superintendent David Cox tells WCBC News that despite the few delays, the overall project schedule hasn’t been compromised…