Melinda Kelleher, Executive Director Downtown Development Commission says all Silva cells for the project are now installed. Street pavers were started on South Liberty Street (because they needed to adjust a few things on North Liberty). Next week underground work for the project will be complete (electric and fiber are all that is left), Paver installation continues on Liberty and Concrete work starts onCentre. Wall restoration on the Mechanic St side of the CBIZ building will begin Monday.