image description

Downtown Cumberland Weekly Construction Update

March 15th, 2024 by WCBC Radio

This week:

  • Roadway and parking area pavers were completed on South Liberty Street.
  • Installation of roadway pavers started on North Liberty Street.
  • Concrete work completed on Baltimore Street between Centre and Liberty.

Next week:

  • Concrete work (curbs, planters, roadway base) will begin on Baltimore Street between Centre and George.
  • Roadway paver installation will continue on North Liberty Street.

We would like to remind everyone that vehicular traffic is prohibited within the construction zone. All pedestrians are encouraged to use sidewalks and only cross the streets at intersections or completed crosswalks.